Romania will submit the fifth payment request under the National Recovery and Resilience Plan (PNRR) on Fridayvalued at 2.84 billion euros and comprising 75 targets and milestones (21 reforms and 54 investments)announced Dragos Pîslaru, the Minister of Investments and European Projects, at a press conference held following the government meeting.
"Today, I can tell you that we are ready with 75 targets and milestonescomprising 21 reforms and 54 investmentsand that we will submit this fifth payment request, valued at 2.84 billion euros, of which 1.65 billion euros is in grants and 433 million euros in loans," stated Pîslaru.
He stated that payment request number 5 is the penultimate one envisaged in the final version of the NRRP, and the grant allocation has remained at 13.57 billion.
Regarding the absorption of non-repayable funds, the minister indicated that it would reach 78% following the fifth payment request, up from 66% prior to its submission.
"I would like to point out that, regarding absorption under the PNRR, prior to payment request no. 5 we were at 66% of the grant allocation, and with payment request no. 5, we will reach 78% of the grant amount," the minister stated.
Following this request, Romania will reach a total of 10.6 billion out of the 13.57 billion. Pîslaru emphasized that, following negotiations with the European Commission, payment requests 5 and 6 remained separate.
"Because Romania firmly maintained the position of decoupling Request 5 from Request 6with Request 5 currently amounting to over 10 billion (specifically 10.6 billion) and Request 6 not being allowed to exceed that figurewe are essentially left with only this 2.58 billion difference to discuss," he explained.
Regarding investments funded through the PNRR, the minister stated that all five grant-funded hospitals would be completed; as for the A7 motorway, two segments have already undergone formal acceptance, while the corresponding document for the third segment is expected to be finalized before August 31.
In the railway sector, "quick-win" projects areaccording to the ministerbeing completed in line with the renegotiated terms, and for railway segments where targets were shifted from kilometer-based metrics to payment-based values, Romania is on track to recover the grants.
"Looking solely at the investment portfolios, I can tell you that, at this moment, the risks of missing out on investments are rather marginal," Pîslaru stated.
Regarding the reforms yet to be finalized, the minister mentioned the hydrogen bill, currently before Parliament, and the wage law, which is in the final drafting stage. He also drew attention to the decarbonization bill. "That amendment must be rejected so that we do not face a problem with this final requirement," the minister added.