Testing of the Alstom TRAXX 3 MS electric locomotive purchased by Romania could last until April next year and will be carried out in accordance with current European legislation, Alstom general manager for Romania, Bulgaria and Moldova Gabriel Stanciu declared on Thursday.
"All the tests related to the technical standards of interoperability, those TSIs, must be completed. As we can see, we are on schedule with the prototype, but a whole series of external factors intervene, related in the first place to the management of Romanian infrastructure, which must provide us with all the data and allow us access to critical areas, so that we can run all the compatibility tests with the Romanian railway network. Then the Romanian Railway Authority, the Romanian Railway Safety Authority step in, alongside other bodies in the categories generically called AsBo, DeBo and so on, to complete all the tests. Our forecast, or as per our current knowledge, is that we will be able to complete the entire process by somewhere in April next year. After that we will be able to register the vehicle and start its commercial operation," declared Gabriel Stanciu.
In his turn, the president of the Railway Reform Authority, Mihai Barbu, said that this is the first of a 16-batch of TRAXX 3 MS electric locomotives purchased, and they will all arrive in Romania by August of next year.
"We want to increase the speed on the railway, we are contracting and purchasing new trains, and we also want all our rolling stock procurement projects to be closely correlated with the rehabilitation of the railway," said Mihai Barbu.
The new electric locomotives mark an important chapter in Romania's passenger rail transport, by increasing the efficiency of the services, reducing pollution and increasing comfort on a series of routes on the electrified public railway network.
These railway vehicles offer a flexible design that uses a robust, modular platform, and are equipped with complex control technology (computer diagnostic/vision, GPS and communication via mobile communications standard), including Alstom's latest generation ERTMS solution.
Comprehensive testing of newly arrived TRAXX 3 MS electric locomotive might take until April next year
București
8°C
Articole Similare

12
Military drone diverted by Ukrainian air defence systems crashes in Romania, says Ministry of Defence
12

9
New alert issued in Tulcea County against the backdrop of the war in Ukraine
9

14
O expoziţie dedicată casei de modă Schiaparelli se deschide la Londra
14

10
Romania's largest ethnology book collection housed at Antim Ivireanul County Library in Ramnicu Valcea
10

6
Educational Center for Permaculture and Healthy Food inaugurated in Buzau
6

14
'Fostering the Future Together' Summit/ Mirabela Gradinaru, alongside Brigitte Macron and Olena Zelenska
14

7
Greek Ambassador: We support Romania's accession to the OECD
7

5
Bucharest Stock Exchange closes higher Wednesday's trading session with trading exceeding 78.6 million lei (15.4 million euros)
5

7
Football: Radu Dragusin - With Türkiye we must prove that we deserve to go to the World Cup
7

11
Predoiu:Respect to all women and men who wear this uniform with dignity and courage
11

11
CONAF president attends 'Women of Influence' Gala in Chicago
11

15
First TRAXX MS3 electric locomotive of 16 to reach Romania in early April
15

6
UDMR leader: Investments in nurseries, kindergartens, schools, sports facilities needed to address demographic problem
6
















Comentează