Transgaz has already completed 330 kilometers of the National Gas Transmission System on the Bulgaria-Romania-Hungary-Austria corridor (BRUA) gas pipeline, a strategic project for the Romanian economy, said on Thursday Prime Minister-designate Ludovic Orban, who attended the inauguration of the gas compressor station in Podisor.
This is the second investment objective in a month within BRUA after the inauguration of the station in Jupa.
"The energy sector can and must be the engine of Romania's economic development, however, it remains far from the potential. In the governing programme we recognise and support the role of Transgaz's strategic projects and, through this important company, whether we are talking about BRUA or Ungheni-Chisinau or gas from the Black Sea, we have the obligation to fight in order to make Romania a safe country in terms of energy," Orban said.
He showed that BRUA project has a total value of 480 million euro, of which 180 million euro represent the grant provided by the European Commission.
"BRUA, phase I is one of the most important strategic projects of Transgaz, which will allow access to new sources and facilitate transmission of Caspian gas toward Central and Eastern Europe," the PM-designate continued.
According to him, the pipeline enables the transmission of 1.5 cubic meters of gas in relation to Bulgaria and 1.75 cubic meters in relation to Hungary.
"Of the 497 kilometers of pipeline between Podisor and Recas, 330 kilometers are already completed. There are three compressor stations, of which the station in Jupa that was inaugurated on 30 September, the one in Podisor [inaugurated] today, 31 October and the one in Bibesti is in progress and respects the chart," the PM-designate added.
Orban showed that BRUA is an extremely ambitious project, "representing the work of thousands of people in dozens of sites."
PM-designate Orban: 330 km of the 479 km of BRUA gas pipeline already completed
Explorează subiectul
București
15°C
Articole Similare

5
Senate passes Unified Digital Design System for state services
5

9
Grindeanu: I met Cristian Anton in Timisoara, I didn't bring him to the Ministry of Transport
9

9
Pîslaru: Any destabilization of Government would be an act of gross irresponsibility
9

14
BNR's forex reserves increase to EUR 67.30 million in March 2026
14

8
MAE/Romania-US Exchange Program, visits by US delegations to institutions, associations, universities
8

8
Robotics team from Arad school qualifies for FIRST Robotics Competition World Championship in the US
8

9
FinMin Nazare: Real test of Romania's economic leadership in 2026 is the ability to maintain fiscal trajectory
9

9
DEER signs 98 million lei contract to modernise control systems, implement ADMS
9

9
Cluj-based Babes-Bolyai University participates in media literacy programme coordinated by Finland
9

8
ICR Tokyo to launch "Japan through Romanian Eyes" debate series on Friday
8

7
Euro trades at RON 5.0985
7

7
Erosion of political stability has repercussions for Romania - Finance Minister Alexandru Nazare
7

8
Romanian, Slovakian engineering companies to supervise together construction of A8 motorway segment
8















Comentează